    SOC 2 Timeline Estimator

    Map your path from today to a delivered SOC 2 report — readiness, fieldwork, and observation window included.

    Your situation

    Your estimated timeline

    7.5–9 months

    1. 1

      Gap assessment & remediation · 4–8 wks

      Close control gaps, finish policies, and stabilize evidence collection.

    2. 2

      Observation window (6 months) · 26 wks

      Controls must operate over the window while evidence accumulates.

    3. 3

      Type 2 fieldwork & report · 3–6 wks

      Auditor tests operating effectiveness across the window, then issues the report.

    Based on standard SOC 2 practice norms (AICPA guidance and typical firm timelines), not measured marketplace statistics. Your auditor confirms the real schedule at scoping.

    Get Matched with Auditors

    Email me this breakdown + matched quotes

    We'll send your phase-by-phase timeline and match you with accredited firms that can hit it.

    Good to know

    • • A Type 1 report can land in weeks; a Type 2 can't be rushed past its observation window — controls must actually operate over the period.
    • • Many companies do a Type 1 first for a quick win, then let the Type 2 window run — that's the combo path above.
    • • Budgeting too? Get your number from the SOC 2 cost calculator at published network rates.